99 FEDERAL PROJECTS WORTH RM12 BLN APPROVED IN SARAWAK

Works Minister Datuk Seri Alexander Nanta Linggi
16/11/2026 03:54 PM

KOTA SAMARAHAN, Nov 16 (Bernama) -- Thirty-five of Sarawak's 99 federal development projects, worth RM12 billion in total, are currently under construction, Works Minister Datuk Seri Alexander Nanta Linggi said.

He said the Sarawak Public Works Department (JKR) had been entrusted with carrying out projects valued at RM50 million and below.

“Construction is under way on 35 of these projects, which have a combined value of RM5 billion,” he said after the handover ceremony for the completed Armed Forces Family Quarters (RKAT) project at Muara Tuang Camp here today.

On contractors' performance, Nanta said his ministry maintains a comprehensive database and internal records on each appointed contractor's capabilities, but does not make the list public to prevent misuse.

He clarified that contractors who finished projects earlier than scheduled would not automatically receive bonuses or be given more work.

“We know which contractors have a proven track record of reliability and can be trusted to complete their work properly, while some do not perform as well,” he said.

Nanta said contractors should not be held solely responsible for project delays, which could also result from external factors such as land acquisition, detailed surveys, utility relocation and changes to the scope of work.

However, contractors would still be held responsible if their own negligence caused the delays, he said.

“We do not want projects to be delayed or face difficulties because of shortcomings in management, finances or the handling of workers on site. Some contractors take on large projects without having sufficient workforce. They must be fully accountable for their responsibilities,” he said.

Nanta earlier witnessed the handover of the completed Muara Tuang Camp RKAT project, worth RM119.1 million. Built on a 28.3-acre site, the project comprises 190 housing units of various categories, equipped with basic facilities including a surau, kindergarten and childcare centre.

He said the project, undertaken by JKR's Special Project Team 2, was completed within the scheduled three years, though a slight extension was granted due to additional work.

-- BERNAMA